Update to VGS 24" and 26" repairs:
 
The 24" line:  Dive boat is expected to be on-site Oct 30th.  Repairs, dewatering and testing expected to take 7 - 10 days.  VGS start-up approximately for the 24" is expected to be Nov 10. 
 
The 26" line - Spud barge delayed until mid November and will require approximately 2 weeks to complete repair and test line.  The 26" will be in service approximately Dec 1.
 
If you have any questions, please call your VGS representative.