Notice

127 Critical Maintenance Initiate 12/19/2008 12/19/2008 12/31/2008
Message

12/19/08

VGS repairs are being completed on the 26" line which will be pressured once repairs are complete at ST151.  These repairs could be completed by Sunday, Dec. 21, at that time the following platforms will be called by pipeline operations to bring production online:

GI45

WD64/65

WD41/42

WD36/39

Once line pressure has reached a sustained level, production will be turned to the Venice plant, at that point there will be another posting.  There will be no sales into the Venice plant until that time.

Please call your VGS representative if you should have any questions.