128 Critical Maintenance Initiate 12/22/2008 12/22/2008 12/31/2008
Message

Repairs on the VGS 26 inch line have been completed, Chevron is in the process of completing their lockout/tagout procedures to allow flow on the 26 inch line again.  VGS will be accepting nominations for line fill only with no condensate injection once we have confirmation from Chevron that the LO/TO procedures have been completed.  Flow into VGS will be stopped when the pipeline has reached 850 psig in order to perform the 2 hour stand up test before being put back into service.