133 Critical Maintenance Initiate 12/26/2008 12/26/2008 12/31/2008
Message

12/26/08  7pm

VGS has completed work on the valve repairs needed on the 26" segment.  Producers from the platforms listed below will be allowed to flow.  Operations will contact the individual platforms, shippers will not nominate to sales to the Venice plant until the pipeline pressure test is complete.

GI45

WD64/65

WD41/42

If you have any questions, please call your VGS representative.