Notice

151 Critical Maintenance Initiate 08/25/2009 08/25/2009 08/31/2009
Message VGS plans to shutdown at about 11 am on Wednesday August 26th for approximately 4 hours for valve work at WD-79.  Shippers will be allowed to flow into the pipeline during the shutdown as the work is expected to be completed and flow re-established to DGS without need for shippers to shut-in.  Shippers should be prepared to shut-in if needed if unexpected complications with the valve repair are incurred."