Notice

171 Critical Force Majeure Initiate 08/27/2011 08/27/2011 12/31/2011
Message

VGS Force Majeure Update #1:

VGS expects to receive the clamp for repairs to the line on Tuesday, August 30th.   After installation, the line will be re-pressured for a 2 hour stand-up test.   Flow is expected to resume by Friday, September 2nd.     Operators will be notified as soon as flow may resume.   Please contact your VGS Representative if you have any questions.