Notice

175 Critical Force Majeure Initiate 09/09/2011 09/09/2011 12/31/2011
Message

Work is progressing and the leak has been located.  Due to the location of the leak, excavation of the site will need to be moved to allow for installation of the clamp.   This process will add approximately 3 days to the timeline .  

Flow is anticipated to resume late during the week of September 12, or early the following week.