Notice

61 Critical Other Terminated 01/04/2006 01/04/2006 02/01/2006
Message

january 4, 2006

 

vgs shippers:

 

as mentioned in yesterday's notice, vgs has encountered problems during the testing of the system.  based upon the analysis of the problems, our current estimate for the completion of repairs on vgs is february 1, 2006.  this estimate is dependent on several factors including, but not limited to, availability of repair materials and contractors and weather conditions.

 

based upon the above, vgs is still unable to take nominations from any receipt points other than the following:

 

south timbalier block 177e - meter #st72841

south timbalier block 151/135 - meter #75825-1,2

 

should you have any questions, please contact your targa gas control representative.