Notice

71 Critical Other Initiate 03/28/2006 03/28/2006 04/30/2006
Message

march 28, 2006

 

vgs shippers:

 

vgs continues efforts to bring the system back on line.  since the last update, vgs has continued to be hampered by weather and equipment problems related to the replacement of the 20" subsea check valve in gi-71.  this update relays the latest estimates on the remaining vgs repairs.

 

additional repairs and/or standup tests remain to occur on the following lines:

 

  1. standup test on the 26" mainline from st-151 comp to wd-41aux (estimated completion is 4-7-06)
  2. replacement of a 20" subsea check valve in gi-71 (estimated completion is 3-30-06)
  3. standup test on the 20" lateral from st-35d to the subsea tie-in at gi-71 (estimated completion is 4-7-06)

 

this estimate is dependent on several factors including, but not limited to, availability of repair materials and contractors and weather conditions.

 

based upon the above, vgs is still unable to take nominations from any receipt points other than the following:

 

south timbalier block 177e - meter #st72841

south timbalier block 151/135 - meter #75825-1,2

south timbalier block 151/148 - meter #75836-1,2

south timbalier block 265 - meter #75833, meter #75834-1,2

south timbalier block 260 - meter #vgs0100

south timbalier block 204/189 - meter #st20800

west delta block 102 - meter #wd10200

west delta block 79 - meter #1213-410

grand isle block 68 - meter #gi68800

west delta block 41/42 - meter #p36-800